CAIRO: The Kuwait Oil Co. has delayed bidding on two of its projects.

Bidding for one of the projects, which include the construction of two 132 kilovolts substations and 33 power lines, has been postponed from Sept. 4 to Oct. 16.

While the other project — supplying sulphuric acid to refineries — has put off its bids for 14 days and rescheduled it for the 8th of September, reported MEED.

Iraq $150 million airport